Procedure For Fiber Optic Installation And Testing

GENERAL REQUIREMENTS


  • Special equipment and trying out tools shall bear legitimate calibration certificate traceable to a national preferred indicating calibration validity and periodically (at the least 12 months) checked via a 3rd birthday party laboratory testing facility
  • Manpower, equipment, equipment and other logistics will be ready and prepared for installation.
  • Fiber optic cable shall be withdrawn after determining inspection document as frequent with cloth receiving inspection report form.
  • Unless in any other case stated, all tests will be conducted by using the Communication web site Engineer and witnessed via the Communication QC Inspector. The check shall be recorded as defined herein.
  • Cable reels shall be shipped and dealt with on the rims of flanges only. Reel shall be greatly surprised all through shipping to prevent damage from load shifting.
  • Splicing methods shall be performed as per available fiber optic cable (FOC) splicing commands or with this procedure. fiber optic certifications